Recently in the case of Shalabh
Nigam vs Orris Infrastructure Pvt. Ltd. & Ors., the Apex Consumer
Commission (NCDRC) , giving hope to lakhs of aggrieved homebuyers, has
quantified a time period of one year for delayed projects beyond which homebuyers/investors
can claim refund from builders.
The Hon’ble Supreme Court and Consumer Courts have repeatedly held that
homebuyers cannot be made to wait indefinitely, but the issue relating to when refund can be claimed in case of delay was
not clarified. The plea was preferred by a Delhi resident Shalabh Nigam, who booked
a flat in 2012 in the luxury housing project, Greenopolis, in Gurgaon being
developed by Orris Infrastructure and 3C Company.
The Buyer had made a payment of around Rs 90 lakh against the total cost
of around Rs 1 crore. As per the Builder-Buyer Agreement, the flat was to be
handed over within 36 months, with a grace period of six months, from the date
of allotment. The Buyer approached NCDRC seeking its direction for either refund or
time-bound possession of the flat when the builder failed to complete the
project within the specified time.
The commission directed the builder to complete the construction and hand
over the flat, complete in all respects as per the agreement, by end of
September 2019 after obtaining occupancy certificate and to pay compensation at
the rate of 6% per year on the total deposit for the delayed period even after
handing over Possession. It further directed the builder that in case of
non-delivery of flat within the deadline prescribed by commission, NCDRC, the
builder will have to refund the entire amount with 10% interest.
The Court further observed -
“It is now established that
allottees have the right to ask for refund if possession is inordinately
delayed, particularly beyond one year,”
On the contention of the builder that
the buyer had discontinued paying installments and if refund is ordered, then
there will be a forfeit of 10% of the amount as earnest money, as per the
agreed clause, the commission rejected the same stating that the installments
were paid up to the 7th stage and the payment was stopped later as
there was no progress in the construction.
Comments
Post a Comment