Police have registered cases  cheating against 27 Builders of Thane, Maharashtra for allegedly forging documents for the registration of their projects with Real Estate Regulatory Authority (RERA).

Police officials told that accused have allegedly cheated home buyers from 27 Villages & Kalyan Dombivli Municipal Corporation (KDMC) as a part of racket. The accused forged the documents to show that the proper permission was taken from Kalyan Dombivli Municipal Corporation for the construction of house & based on that they got the RERA Registration.

The developers were involved in fraud from 2017 to 2022 & each  homebuyer paid somewhere around Rs. 25 lakhs to 35 lakhs for a home.

A case has been registered for the above case, but no arrest has been made so far. 

Comments

Popular posts from this blog

RERA Awards Rs. 65 Lakhs Compensation to Homebuyer for 9 Years Delay in Flat Possession

  CA Ramesh Agrawal In a recent decision, the Haryana Real Estate Regulatory Authority (HRERA) has directed a builder to compensate a homebuyer with ₹65 lakh for an inordinate delay of over nine years in handing over a flat in Gurugram. Key Highlights: Background of the Case : The homebuyer had booked a flat in 2013, with the developer promising possession within a stipulated timeframe i.e., 7 th December 2015. However, the possession was delayed by more than nine years. Developer's Justifications : The builder attributed the delay to unforeseen circumstances, including the COVID-19 pandemic, the demise of the chairman of environmental impact assessment (EIA) committee, and inadequate water supply. H-RERA's Verdict : After reviewing the case, HRERA rejected the developer's justifications, deeming them insufficient to warrant such a prolonged delay. The authority emphasized that the reasons cited did not qualify as fo...

Municipality Demolishes Illegal & Unsafe Structures

  CA Ramesh Agrawal The Sambhajinagar Municipal Corporation (CSMC) has started an anti-encroachment campaign, to keep the city clean, safer, free up public space, etc. Details of the same are mentioned as below: - Drive Moves To Gulmandi Area: - After cleaning up areas like Beed Bypass and Mukundwadi, now the clean campaign has moved to Gulmandi area, which is busy & crowded market zone. The move shows that the Authorities are serious for removing illegal building all across the city. Illegal Constructions & extension demolished: - The Authorities have targeted illegal buildings & extension of around 25 Shops in bustling Rangar Galli Market & its surrounding areas. During the operation demolition of a run-down building was carried out with the presence of police. Ongoing Efforts : - Additional Municipal Commissioner, Mr. Santosh Wahule explained that this campaign in Gulmandi was carried out on the instructions of the Civic Chief G. Sreekanth. This clean campaign ...

Mandatory Uploading of Occupancy and Completion Certificates

  CA Ramesh Agrawal In a significant move to enhance transparency and protect homebuyers' interests, the Odisha Real Estate Regulatory Authority (ORERA) has mandated that developers upload occupancy and completion certificates of housing projects onto its official website. This directive aims to ensure that residential projects comply with established norms and are fit for habitation.​ Definition of Certificates: Completion Certificate: A legal document confirming that a building has been constructed in accordance with approved plans and complies with all applicable regulations. Occupancy Certificate: A document issued by the local authority certifying that a building is suitable for occupation, ensuring it meets all necessary safety and habitability standards. Mandatory Upload Requirement: Developers are now required to upload both completion and occupancy certificates onto the ORERA website upon proj...